You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project.

What is the only output of the quantitative risk analysis process?

A.
Probability of reaching project objectives
Answers
A.
Probability of reaching project objectives
B.
Risk contingency reserve
Answers
B.
Risk contingency reserve
C.
Risk response
Answers
C.
Risk response
D.
Risk register updates
Answers
D.
Risk register updates
Suggested answer: D