You work as the project manager for Bluewell Inc. You are working on NGQQ Projectyou're your company. You have completed the risk analysis processes for the risk events. You and the project team have created risk responses for most of the identified project risks. Which of the following risk response planning techniques will you use to shift the impact of a threat to a third party, together with the responses?

A.
Risk acceptance
Answers
A.
Risk acceptance
B.
Risk avoidance
Answers
B.
Risk avoidance
C.
Risk transference
Answers
C.
Risk transference
D.
Risk mitigation
Answers
D.
Risk mitigation
Suggested answer: C