You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register?

Each correct answer represents a complete solution. Choose two.

A.
List of potential responses
Answers
A.
List of potential responses
B.
List of identified risks
Answers
B.
List of identified risks
C.
List of mitigation techniques
Answers
C.
List of mitigation techniques
D.
List of key stakeholders
Answers
D.
List of key stakeholders
Suggested answer: A, B