The Software Configuration Management (SCM) process defines the need to trace changes, and the ability to verify that the final delivered software has all of the planned enhancements that are supposed to be included in the release. What are the procedures that must be defined for each software project to ensure that a sound SCM process is implemented?

Each correct answer represents a complete solution. Choose all that apply.

A.
Configuration status accounting
Answers
A.
Configuration status accounting
B.
Configuration change control
Answers
B.
Configuration change control
C.
Configuration deployment
Answers
C.
Configuration deployment
D.
Configuration audits
Answers
D.
Configuration audits
E.
Configuration identification
Answers
E.
Configuration identification
F.
Configuration implementation
Answers
F.
Configuration implementation
Suggested answer: A, B, D, E