ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 6 - CISSP-ISSEP discussion

Report
Export

Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid configuration management activities except for which one

A.
Configuration Item Costing
Answers
A.
Configuration Item Costing
B.
Configuration Identification
Answers
B.
Configuration Identification
C.
Configuration Verification and Auditing
Answers
C.
Configuration Verification and Auditing
D.
Configuration Status Accounting
Answers
D.
Configuration Status Accounting
Suggested answer: A
asked 18/09/2024
Sundarrajan Mugunthan
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first