Which of the following statements is true about residual risks

A.
It can be considered as an indicator of threats coupled with vulnerability.
Answers
A.
It can be considered as an indicator of threats coupled with vulnerability.
B.
It is a weakness or lack of safeguard that can be exploited by a threat.
Answers
B.
It is a weakness or lack of safeguard that can be exploited by a threat.
C.
It is the probabilistic risk after implementing all security measures.
Answers
C.
It is the probabilistic risk after implementing all security measures.
D.
It is the probabilistic risk before implementing all security measures.
Answers
D.
It is the probabilistic risk before implementing all security measures.
Suggested answer: C