Question 33 - CISSP-ISSEP discussion
Which of the following documents is described in the statement below It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning.
A.
Risk management plan
B.
Project charter
C.
Quality management plan
D.
Risk register
Your answer: