Which of the following tasks prepares the technical management plan in planning the technical effort

A.
Task 10
Answers
A.
Task 10
B.
Task 9
Answers
B.
Task 9
C.
Task 7
Answers
C.
Task 7
D.
Task 8
Answers
D.
Task 8
Suggested answer: B