Question 212 - CISSP-ISSEP discussion
You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control
A.
Quantitative risk analysis
B.
Risk audits
C.
Requested changes
D.
Qualitative risk analysis
Your answer: