You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:

How much capital should the project set aside for the risk contingency reserve?

A.
$142,000
Answers
A.
$142,000
B.
$232,000
Answers
B.
$232,000
C.
$41,750
Answers
C.
$41,750
D.
$23,750
Answers
D.
$23,750
Suggested answer: D