List of questions
Related questions
Question 23 - CISSP-ISSMP discussion
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:
How much capital should the project set aside for the risk contingency reserve?
A.
$142,000
B.
$232,000
C.
$41,750
D.
$23,750
Your answer:
0 comments
Sorted by
Leave a comment first