ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 131 - CISSP-ISSMP discussion

Report
Export

Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

A.
Earned value management
Answers
A.
Earned value management
B.
Risk audit
Answers
B.
Risk audit
C.
Technical performance measurement
Answers
C.
Technical performance measurement
D.
Corrective action
Answers
D.
Corrective action
Suggested answer: D
asked 18/09/2024
AshokBabu Kumili
43 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first