Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."

A.
Monitor and Control Risks
Answers
A.
Monitor and Control Risks
B.
Identify Risks
Answers
B.
Identify Risks
C.
Perform Qualitative Risk Analysis
Answers
C.
Perform Qualitative Risk Analysis
D.
Perform Quantitative Risk Analysis
Answers
D.
Perform Quantitative Risk Analysis
Suggested answer: A