You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?

A.
Risk management plan
Answers
A.
Risk management plan
B.
Lessons learned documentation
Answers
B.
Lessons learned documentation
C.
Risk register
Answers
C.
Risk register
D.
Stakeholder management strategy
Answers
D.
Stakeholder management strategy
Suggested answer: C