In which of the following SDLC phases is the system's security features configured and enabled, the system is tested and installed or fielded, and the system is authorized for processing?

A.
Initiation Phase
Answers
A.
Initiation Phase
B.
Development/Acquisition Phase
Answers
B.
Development/Acquisition Phase
C.
Implementation Phase
Answers
C.
Implementation Phase
D.
Operation/Maintenance Phase
Answers
D.
Operation/Maintenance Phase
Suggested answer: C