You are documenting your organization's change control procedures for project management. What portion of the change control process oversees features and functions of the product scope?

A.
Configuration management
Answers
A.
Configuration management
B.
Product scope management is outside the concerns of the project.
Answers
B.
Product scope management is outside the concerns of the project.
C.
Scope change control system
Answers
C.
Scope change control system
D.
Project integration management
Answers
D.
Project integration management
Suggested answer: A