You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?
A.
Identification information for each stakeholder
B.
Assessment information of the stakeholders' major requirements, expectations, and potential influence
C.
Stakeholder classification of their role in the project
D.
Stakeholder management strategy