Which of the following documents is described in the statement below? "It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."

A.
Risk register
Answers
A.
Risk register
B.
Risk management plan
Answers
B.
Risk management plan
C.
Quality management plan
Answers
C.
Quality management plan
D.
Project charter
Answers
D.
Project charter
Suggested answer: A