Question 153 - CISSP-ISSMP discussion
Which of the following elements of BCP process includes the areas of plan implementation, plan testing, and ongoing plan maintenance, and also involves defining and documenting the continuity strategy?
A.
Business continuity plan development
B.
Business impact assessment
C.
Scope and plan initiation
D.
Plan approval and implementation