You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?

A.
Cost plus incentive fee
Answers
A.
Cost plus incentive fee
B.
Fixed fee
Answers
B.
Fixed fee
C.
Cost plus percentage of costs
Answers
C.
Cost plus percentage of costs
D.
Time and materials
Answers
D.
Time and materials
Suggested answer: C