Mark is the project manager of the NHQ project in Spartech Inc. The project has an asset valued at $195,000 and is subjected to an exposure factor of 35 percent. What will be the Single Loss Expectancy of the project?

A.
$92,600
Answers
A.
$92,600
B.
$67,250
Answers
B.
$67,250
C.
$68,250
Answers
C.
$68,250
D.
$72,650
Answers
D.
$72,650
Suggested answer: C