Tomas is the project manager of the QWS Project and is worried that the project stakeholders will want to change the project scope frequently. His fear is based on the many open issues in the project and how the resolution of the issues may lead to additional project changes. On what document are Tomas and the stakeholders working in this scenario?
A.
Communications management plan
B.
Change management plan
C.
Issue log
D.
Risk management plan