You work as the Senior Project manager in Dotcoiss Inc. Your company has started a software project using configuration management and has completed 70%of it. You need to ensure that the network infrastructure devices and networking standards used in this project are installed in accordance with the requirements of its detailed project design documentation. Which of the following procedures will you employ to accomplish the task?

A.
Configuration identification
Answers
A.
Configuration identification
B.
Physical configuration audit
Answers
B.
Physical configuration audit
C.
Configuration control
Answers
C.
Configuration control
D.
Functional configuration audit
Answers
D.
Functional configuration audit
Suggested answer: B