Why might static analysis be used on an Agile project'

SELECT ONE OPTION

A.
To implement a test-driven approach at the component level
Answers
A.
To implement a test-driven approach at the component level
B.
To manually identify potential defects and thus avoid technical debt
Answers
B.
To manually identify potential defects and thus avoid technical debt
C.
To clarify and simplify code design without changing its behavior
Answers
C.
To clarify and simplify code design without changing its behavior
D.
To identify the causes of technical debt through the use of tools
Answers
D.
To identify the causes of technical debt through the use of tools
Suggested answer: D

Explanation:

Static analysis is used on an Agile project to identify the causes of technical debt through the use of tools. This approach allows teams to detect potential issues in code that could lead to technical debt if not addressed promptly, thus maintaining the health of the codebase as it evolves rapidly in Agile environments .