Which of the following is a common technical issue that causes automation projects to fail to meet the planned return on investment?

A.
Insufficient planning for usability
Answers
A.
Insufficient planning for usability
B.
Failing to design for maintainability
Answers
B.
Failing to design for maintainability
C.
Designing for keyword-driven use
Answers
C.
Designing for keyword-driven use
D.
Using capture-playback to do the initial capture of the window objects
Answers
D.
Using capture-playback to do the initial capture of the window objects
Suggested answer: B

Explanation:

A common technical issue causing automation projects to fail in delivering the planned return on investment is the lack of maintainability in their design. Automation frameworks and scripts that are not designed with maintainability in mind can become cumbersome to update and scale as the software evolves. This results in increased costs and effort over time to keep the automation relevant and effective, which can erode the expected returns on investment from the automation initiative .