List of questions
Related questions
Question 115 - CTFL-2018 discussion
Refer to the exhibit
The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window
The first activity is to run any re-tests, followed by the regression test script. Users have supplied their priority order to tests.
Which of the following gives an appropriate test execution schedule, taking account of the prioritisation and other constraints? [K3]
A.
b, c, g, d, e, i, a, f, h
B.
a, c, d, b, g, e, i, f, h
C.
c, a, d, b, e, g, i, h, f
D.
d, c, a, e, b, g, i, f, h
Your answer:
0 comments
Sorted by
Leave a comment first