List of questions
Related questions
Question 119 - CTFL-2018 discussion
Test script TransVal 3.1 tests transaction validation via screen TRN 003B. According to the specification (PID ver 1.3 10b iv) the validation screen should not accept future dated transactions. Test script TransVal 3.1 passes. Test script eod 1.4 tests end of day processing and is run after the execution of TransVal 3.1 using data entered during that test
Which of the following is the BEST detail on an incident report? [K3]
A.
Title. End of Day failure.. Reproducible. Yes. Description. Script eod 1.4 fails when the first transaction of the day is a future dated transaction. Screen shot of the failure attached.
B.
Title. Transaction input screen validation..Reproducible. Yes. Description. Script eod 1..4 fails . Screen shot of the failure attached. Validation of transaction entryon screen TRN-003B should not allow future dated transactions -- see PID ver 1.3 para 10b iv.
C.
Title. Screen TRN-003B validation of transaction date.. Reproducible. No. Description. When a future dated transaction is processed by the end of day process, a failure can occur. This does not always happen. Screen shot of the failure attached.
D.
Title. Screen TRN-003B validation of transaction date. Reproducible. Yes. Description. Script eod 1.4 fails when the first transaction of the day is a future dated transaction. Screen shot of the failure attached. Validation of transaction entry on screen TRN-003B should not allow future dated transactions -- see PID ver 1.3 para 10b iv.
Your answer:
0 comments
Sorted by
Leave a comment first