An Incident Management tool implements the following defect states Open. Assigned. Solved. Closed.

Consider the following defect report:

Id: T000561

Test Object: 'Warehouse Management' application

Tester name : John Bishop

Date: 10th, April 2010

Test Case MRT5561

Status: OPEN

Severity Serious

Priority:

Problem : After inputting the Total Quantity item = 450 in the SV034 screen . the system shows an unexpected Error message = 47

Correction:

Developer name:

Closing date

Which of the following is a valid criticism of this report?

A.
The Priority, the Correction description and the Developer name are missing
Answers
A.
The Priority, the Correction description and the Developer name are missing
B.
The description is not highlighting the source of the problem
Answers
B.
The description is not highlighting the source of the problem
C.
The version of the application is missing
Answers
C.
The version of the application is missing
D.
There is no link to the applicable requirement (traceability)
Answers
D.
There is no link to the applicable requirement (traceability)
Suggested answer: C

Explanation:

The version of the application is missing from the defect report. This is a valid criticism because it is important to specify which version of the software was tested when the defect was found, as this can help to identify and reproduce the defect, and to verify if it has been fixed in a later version.