Which of the following lists represents the correct sequence of the main activities of the fundamental test process (leaving out the activity of control which should take place in parallel to all the other activities)?
A.
Planning, analysis and reporting, design and implementation, execution, test closure activities, evaluating exit criteria.
B.
Planning, analysis, design and implementation, execution, logging, test closure activities, evaluating exit criteria.
C.
Planning, analysis and design, execution, logging and reporting, regression testing
D.
Planning, analysis and design, implementation and execution, evaluation exit criteria and reporting, test closure activities