Question 263 - CTFL-2018 discussion
Which of the following activities do NOT belong to test implementation and execution?
A.
Checking if the preconditions of test execution have been met
B.
Logging of test results
C.
Test data generation
D.
Prioritizing test conditions
Your answer: