Which of the following would NOT typically be covered in a test summary report?

A.
The risks associated with unresolved defects found during testing.
Answers
A.
The risks associated with unresolved defects found during testing.
B.
Any features of the system that were not tested along with reasons.
Answers
B.
Any features of the system that were not tested along with reasons.
C.
Whether there is any economic benefit in continuing testing beyond the planned date.
Answers
C.
Whether there is any economic benefit in continuing testing beyond the planned date.
D.
An analysis of lessons learned to determine changes for future projects.
Answers
D.
An analysis of lessons learned to determine changes for future projects.
Suggested answer: C

Explanation:

According to the syllabus, a test summary report is a document that summarizes the results and activities of a completed test level. It typically includes information such as test objectives, test items, test environment, test cases executed, defects found, incidents raised, and lessons learned. The answer C is incorrect because it would not typically be covered in a test summary report. The economic benefit of continuing testing beyond the planned date is not a relevant information for a completed test level, as it is more related to project management decisions. The other answers are correct because they are examples of information that would typically be covered in a test summary report.