Question 340 - CTFL-2018 discussion
Which two of the following events would represent triggers for maintenance testing?
a) Upgrading the production system's database for the latest Oracle release
b) Migrating tests from a spreadsheet to the new test management tool
c) An urgent fix to a new application before its initial release to production
d) Simplifying the requirements to make them easier to analyse and review
e) Retirement of a live application that no longer has business benefit
A.
a and b
B.
a and e
C.
c and d
D.
c and e