Which one of the following would you typically expect to find in a test completion report for a test level?

A.
Factors that are currently impeding test progress and the tests planned for the following day.
Answers
A.
Factors that are currently impeding test progress and the tests planned for the following day.
B.
A summary of the testing performed and any deviations from the schedule, duration or effort of test activities.
Answers
B.
A summary of the testing performed and any deviations from the schedule, duration or effort of test activities.
C.
The planned overall approach for testing and the resources required to perform the various test activities.
Answers
C.
The planned overall approach for testing and the resources required to perform the various test activities.
D.
The proposed exit criteria and metrics reports for review and agreement by the stakeholders.
Answers
D.
The proposed exit criteria and metrics reports for review and agreement by the stakeholders.
Suggested answer: B

Explanation:

A test completion report for a test level typically includes a summary of all the testing activities that have been performed. It should detail any deviations from the original test schedule, including any changes in the planned duration or effort that were required to complete the test activities. This report serves as a record of what was tested, how it was tested, and any issues that were encountered.