Question 351 - CTFL-2018 discussion
Which of the following BEST defines risk level?
A.
Risk level Is calculated by adding the probabilities of all planned risks to a project
B.
Risk level Is determined by the likelihood of an event happening and the impact or harm from that event
C.
Risk level Is calculated by dividing the sum of all known risks by the sum of all unknown risks
D.
Risk level is determined by calculating the absolute value of the sum of all potential issues that may occur on the project