In a sprint planning, the product owner presents a user story written on a card. The team starts having a discussion with the product owner to get an understanding on how the software should work.

The user story written on the card is:

'As a customer, I want to subscribe to the mailing list so that I can receive the latest deal in an email.'

By applying the 3C concept, which ONE of the following statements is CORRECT?

SELECT ONE OPTION

A.
Conversation should include the acceptance criteria discussion.
Answers
A.
Conversation should include the acceptance criteria discussion.
B.
Product owner has written a user story and confirmation is not needed.
Answers
B.
Product owner has written a user story and confirmation is not needed.
C.
The card should contain requirements not the user story.
Answers
C.
The card should contain requirements not the user story.
D.
The conversation is not required and the team should start developing.
Answers
D.
The conversation is not required and the team should start developing.
Suggested answer: A

Explanation:

The 3C concept in Agile development refers to Card, Conversation, and Confirmation. This concept emphasizes the collaborative and iterative nature of defining user stories and their acceptance criteria in Agile projects. In the context of the provided user story, 'As a customer, I want to subscribe to the mailing list so that I can receive the latest deal in an email,' option A is correct. The conversation should include the acceptance criteria discussion, which is an integral part of the 3C concept.

The Card represents the user story itself, which is a brief statement describing a feature or requirement from the user's perspective. The Conversation involves discussions between the development team and the product owner (or other stakeholders) to clarify the details and ensure a mutual understanding of the user story. This conversation is crucial for exploring the user story's implications, discussing potential implementation approaches, and agreeing on the acceptance criteria that define when the story is considered complete and satisfactory.

Confirmation involves agreeing on and documenting the acceptance criteria that emerge from the conversation. These criteria serve as a checklist to ensure that the implemented feature meets the user's needs and expectations as defined in the user story.

Option A is the verified answer because it accurately reflects the importance of including acceptance criteria discussions in the conversation phase of the 3C concept. This practice aligns with Agile principles by ensuring clarity, shared understanding, and a focus on delivering value to the customer.

asked 18/09/2024