Which of the following would provide the MOST independence for testers working with agile teams?

SELECT ONE OPTION

A.
Testers from an independent test team who do not get involved with the Agile team, but are assigned to do System Testing once all sprints are completed.
Answers
A.
Testers from an independent test team who do not get involved with the Agile team, but are assigned to do System Testing once all sprints are completed.
B.
Testers are fully embedded in each Agile team to perform many of the testing tasks.
Answers
B.
Testers are fully embedded in each Agile team to perform many of the testing tasks.
C.
Testers from an independent test team are assigned on-demand for the final days of each sprint.
Answers
C.
Testers from an independent test team are assigned on-demand for the final days of each sprint.
D.
Testers from an independent test team are assigned to the Agile team at the beginning of the project, returning for re assignment to a new agile team.
Answers
D.
Testers from an independent test team are assigned to the Agile team at the beginning of the project, returning for re assignment to a new agile team.
Suggested answer: B

Explanation:

In Agile project environments, embedding testers within the Agile teams promotes close collaboration, immediate feedback, and continuous improvement, essential principles of Agile methodologies. This integration enables testers to be involved in all stages of the development process, from planning and design to execution and review, facilitating early detection of defects, understanding of user requirements, and adherence to quality standards. The Agile Manifesto emphasizes individuals and interactions over processes and tools, advocating for collaborative team environments where business people and developers work together daily throughout the project. This approach contrasts with traditional methods where testing is often conducted in isolation or after development phases, potentially leading to delays and reduced quality due to the late discovery of issues.