The Kaizen feedback loop can be summarized as:

A.
Plan, Do, Monitor. Study
Answers
A.
Plan, Do, Monitor. Study
B.
Plat. Implement Demo. Study
Answers
B.
Plat. Implement Demo. Study
C.
Plan, Do. Study. Act
Answers
C.
Plan, Do. Study. Act
D.
Study. Act. React, Demo
Answers
D.
Study. Act. React, Demo
Suggested answer: C

Explanation:

The Kaizen feedback loop is commonly summarized as Plan, Do, Study, Act (PDSA). This cycle is used for continuous improvement and problem-solving, where:

Plan: Identify a goal or process and plan a change.

Do: Implement the change on a small scale.

Study: Observe and analyze the results of the change.

Act: Decide on necessary adjustments and standardize the successful changes.

Other options do not correctly capture the Kaizen loop:

A . Plan, Do, Monitor, Study incorrectly places 'Monitor'.

B . Plat, Implement Demo, Study mixes unrelated steps.

D . Study, Act, React, Demo does not follow the correct logical order of the Kaizen feedback loop.

Thus, the correct answer is C. Plan, Do, Study, Act.