A team has completed the work in their iteration backlog earlier than expected. There's still three days left of the iteration, what should the team do now?

A.
Work on noncritical tasks until the product owner can them more work.
Answers
A.
Work on noncritical tasks until the product owner can them more work.
B.
Wait for the other groups to complete their work prior to doing anything else.
Answers
B.
Wait for the other groups to complete their work prior to doing anything else.
C.
Work with the product owner to pull more work from the product backlog into their iteration backlog.
Answers
C.
Work with the product owner to pull more work from the product backlog into their iteration backlog.
D.
Report the differences in completion time so the next iteration can be planned more efficiently.
Answers
D.
Report the differences in completion time so the next iteration can be planned more efficiently.
Suggested answer: D