List of questions
Related questions
Question 192 - DASSM discussion
What is the primary risk addressed by the stakeholder vision milestone?
A.
That your architectural strategy is likely to work
B.
That your primary stakeholders agree to your strategy
C.
That the business case for the project is viable
D.
That a release plan for the project is realistic
Your answer: