Limiting the work-in-progress is an important factor in optimizing flow. How does reducing work-inprogress help?

A.
Pursue multiple goals at a time
Answers
A.
Pursue multiple goals at a time
B.
Create focus
Answers
B.
Create focus
C.
Preventing priority changes
Answers
C.
Preventing priority changes
D.
Respect the timebox
Answers
D.
Respect the timebox
Suggested answer: B