What may NOT be decided during the INCEPTION stage of a Disciplined Agile project?

A.
Test strategy
Answers
A.
Test strategy
B.
Deployment strategy
Answers
B.
Deployment strategy
C.
Initial architecture
Answers
C.
Initial architecture
D.
High level scope
Answers
D.
High level scope
Suggested answer: B