How do you know that you are finished estimating your user stories using the "Team Estimation" technique?

A.
There are no more user stories left to estimate, and no team member wishes to move a card
Answers
A.
There are no more user stories left to estimate, and no team member wishes to move a card
B.
You have spent the one hour set aside for planning
Answers
B.
You have spent the one hour set aside for planning
C.
The Product Owner is done estimating all the user stories
Answers
C.
The Product Owner is done estimating all the user stories
Suggested answer: A