Universal Containers (UC) deploys major releases on a monthly schedule. In recent months, the team has noticed the deployment time has increased two-fold from 2 hours to 4 hours .The team wants to get back to reasonable deployment times. Which three issues could be affecting their deployment times? Choose 3 ans
A.
The number and complexity of Apex tests will have a large impact on the deployment time.
B.
Some components profiles, custom junction objects, and fields take longer to process than others.
C.
The deployments are being scheduled during off peak hours, which is not the best time.
D.
Users are working in the org during deployment locking can affect users and the deployment.
E.
The team is highly constrained with pre-deployment and post-deployment changes.