List of questions
Related questions
Question 53 - Certified Development Lifecycle and Deployment Architect discussion
Universal Containers is in the final stages of building a new application to track custom containers.
During a review of the application, a business subject Matter Expert mentioned that it would be nice to be able to track additional container types beyond what was originally scoped during the plan and design phase. Which two actions should be performed to mitigate the risk? Choose 2 answers.
A.
Escalate and communicate to stakeholders the risk and mitigate it by allocating additional resources to support the new requirement based on stakeholders input.
B.
Have a discussion with the business subject Matter Expert and communicate that the Salesforce has limitations in supporting such a feature to mitigate the risk.
C.
Escalate and communicate to stakeholders the risk and mitigate it by extending the timeline of the project to support the new requirement based on stakeholders input.
D.
Have a discussion with the business subject Matter Expert and communicate that anew developer environment will be needed to mitigate the risk.
Your answer:
0 comments
Sorted by
Leave a comment first