In Architect has been working on a large project for the past 6 months. This project must be live by the end of the current month. Which two planning techniques should the Architect use to ensure all metadata changes deploy smoothly and on time? Choose 2 answers

A.
Ensure all code that is being deployed is checked into source control
Answers
A.
Ensure all code that is being deployed is checked into source control
B.
Validate the final deployment package against production prior to go-live
Answers
B.
Validate the final deployment package against production prior to go-live
C.
Create a new sandbox and perform a test deployment to that environment
Answers
C.
Create a new sandbox and perform a test deployment to that environment
D.
Upload a change set from sandbox to production as early as possible
Answers
D.
Upload a change set from sandbox to production as early as possible
Suggested answer: A, B