Universal Containers is building a new complex integration to a legacy system. the legacy system is also going through a major upgrade. Senior leadership has committed to the board that the combined programs will be completed on time. What is the risk with this plan?
A.
The deadline is scheduled during a Salesforce release
B.
The project team has decided to use the Waterfall methodology
C.
The legacy system team is using an Agile methodology
D.
Multiple work -streams with dependencies could impact the go-live