Which two project situations favor an Agile methodology? Choose 2 answers

A.
A digitization project to update an existing customer -facing process and enable quick adjustments
Answers
A.
A digitization project to update an existing customer -facing process and enable quick adjustments
B.
A project to be executed by a third party, with a fixed and formal scope, budget, and timeline
Answers
B.
A project to be executed by a third party, with a fixed and formal scope, budget, and timeline
C.
An environment with a heavy investment in DevOps capabilities for rapid testing and deployment
Answers
C.
An environment with a heavy investment in DevOps capabilities for rapid testing and deployment
D.
A project with well-defined requirements and complex interactions between front- and back -end systems
Answers
D.
A project with well-defined requirements and complex interactions between front- and back -end systems