Universal Containers (UC) is developing a new Customer Community. Requirements for the Community are not fully defined. UC is planning on using an Agile methodology for this work and has promised delivery of the complete system in three months. What are two risks associated with this approach? Choose 2 answers
A.
The functionality that can be delivered in 3 months is unknown, and may not meet the needs of the business
B.
Given the lack of requirements and the three-month timeline commitment, the project may not be feasible
C.
Agile is not an appropriate development methodology for Customer Community implementations
D.
Agile does not allow for changes to requirements, so customers might not like the resulting solution