The CTO at Universal Containers decided to implement the Scrum framework for its agile teams, and communicated a set of Scrum principles to the company.

Which describes a Scrum principle?

A.
Deliver working software, so if a software component is working, avoid changing it.
Answers
A.
Deliver working software, so if a software component is working, avoid changing it.
B.
Respect other teams by not doing their work (a developer should not test the software).
Answers
B.
Respect other teams by not doing their work (a developer should not test the software).
C.
Create transparency by being honest and clear about timing, planning, and obstacles.
Answers
C.
Create transparency by being honest and clear about timing, planning, and obstacles.
D.
Embrace change by working on a different scope every day.
Answers
D.
Embrace change by working on a different scope every day.
Suggested answer: C