Universal Containers CUC) Customer Community is scheduled to go live in the Europe, Middle East, and Africa (EMEA) region in 3 months. UC follows a typical centralized governance model. Two weeks ago, the project stakeholders informed the project team about the recent changes in mandatory compliance requirements needed to go live. The project team analyzed the requirements and have estimated additional budget needs of 30^0 of the project cost for incorporating the compliance requirements.

Which management team is empowered to approve this additional budget requirements?

A.
Security Review Committee
Answers
A.
Security Review Committee
B.
Project Management Committee
Answers
B.
Project Management Committee
C.
Executive Steering Committee
Answers
C.
Executive Steering Committee
D.
Change Control Board
Answers
D.
Change Control Board
Suggested answer: C