Universal Containers has many backlog items and competing stakeholders who cannot agree on priority.

What should an architect do to overcome this?

A.
Facilitate the design of a prioritization model with the stakeholders.
Answers
A.
Facilitate the design of a prioritization model with the stakeholders.
B.
Organize a sprint planning meeting with the Scrum team.
Answers
B.
Organize a sprint planning meeting with the Scrum team.
C.
Take over prioritization for the stakeholders.
Answers
C.
Take over prioritization for the stakeholders.
D.
Allow the delivery teams to pick the best work for the business.
Answers
D.
Allow the delivery teams to pick the best work for the business.
Suggested answer: A